MEDIATRACNET
To boost electricity transmission capacity in the country, the Transmission Company of Nigeria (TCN) on Saturday took delivery of 15 new power transformers in Lagos.
The delivery of the transformers were 2from the Apapa port, Lagos, earlier last week.
The spokesperson of TCN, Ndidi Mbah said the transformers comprises 10 Nos. 60MVA 132/33kV and five Nos. 150MVA 330/132kV capacity transformers delivered to TCN Central Store in Ojo, Lagos State, for onward delivery to various TCN project sites nationwide.
Mbah quoted the Ag. MD/CEO, TCN, Sule Abdulaziz, as saying that the contract for the supply of the transformers was under the Nigerian Electricity Transmission Project (NETAP) funded by the World Bank.
However, he said TCN is expected to take a decision on the project site the transformers would be installed.
He informed that on installation and connection to the grid, the 10 Nos 60MVA 132/33kV power transformers and the five (5) 150MVA 330/132kV transformers would add 637MW and 850MW respectively to the transmission network, consequently increasing the total capacity of the transmission system by 1487MW, while ensuring N-1 reliability criteria in the substations, which is strategic in enhancing grid stability.
Abdulaziz noted that earlier in August last year, the World Bank also funded transformer supply contracts which brought in ten (10) number 60MVA132/33kV transformers and twenty-five (25 number) earthing transformers.
Out of the ten 60MVA transformers, five were installed in Karu and Gombe Substations, two (2Nos) are currently being installed in Kano and one in Lagos State.
“This is the first time in the history of TCN that it took delivery of large numbers of transformers within a short period. These are milestone achievements for TCN, as it strives to implement its short-term development plan under the Nigerian Electricity Grid Maintenance, Expansion and Rehabilitation Programme (NEGMERP). The World Bank-sponsored NETAP project is only one of the TCN donor-funded projects aimed at expanding the transmission grid, while also prioritizing maintenance of the existing transmission infrastructures” he said.
TCN is equally executing several projects funded by the Agence Français de Développement (AFD). On the other hand, processes for project’s funded by the African Development Bank (AfDB) is progressing very fast and TCN will soon sign contracts for 330kV & 132kV Substations. Meanwhile, the procurement of consultants for projects funded by the Japan International Cooperation Agency (JICA), would soon commence.